Already Completed
Click here to expand and explore our progress so far!
Q3 2023: JUL-SEP
RESIDENT MOVE-OUT & PRE-DEMOLITION WORK
- Install sound wall at St. James (prior to start of school year)
- Demolition of Stevens Ave. property
- Final resident move-outs
- Ongoing security patrols and building maintenance
- Lead/asbestos remediation begins
- Utility disconnection/shutoffs
Q4 2023: OCT-DEC
DEMOLITION AND STEVENS AVE. GRADING
- Lead/asbestos remediation and utility disconnection/shutoff continues
- Building demolition begins
- Site demo and tree removal
- Grading of Stevens Ave. access driveway for affordable housing site
- Fencing installation along Nardo Ave.
Coming Up
Next steps in the revitalization project
Q1 2024: JAN-MAR
GRADING AND UTILITY INSTALLATION
- Grading and soil export begins
- Start of retaining wall construction
- Underground utility installation on Stevens Ave. access driveway
- Stevens Ave access road final paving.
Q2 2024: APR-JUN
GRADING CONTINUED AND BUILDING FOUNDATIONS
- Grading and soil export continues
- On-site retaining wall construction
- Access driveway from Stevens Ave. complete
- Internal underground utility work begins
- Prepare building foundation pads
Q3 2024: July-Sep
GRADING AND BUILDING FOUNDATIONS CONTINUED
- Anticipated soil mass export completion
- On-site retaining wall construction continued
- Internal underground utility work continued
- Ongoing building foundation pad construction