Already Completed
Click here to expand and explore our progress so far!
Q3 2023: JUL-SEP
RESIDENT MOVE-OUT & PRE-DEMOLITION WORK
- Install sound wall at St. James (prior to start of school year)
- Demolition of Stevens Ave. property
- Final resident move-outs
- Ongoing security patrols and building maintenance
- Lead/asbestos remediation begins
- Utility disconnection/shutoffs
Q4 2023: OCT-DEC
DEMOLITION AND STEVENS AVE. GRADING
- Lead/asbestos remediation and utility disconnection/shutoff continues
- Building demolition begins
- Site demo and tree removal
- Grading of Stevens Ave. access driveway for affordable housing site
- Fencing installation along Nardo Ave.
Q1 2024: JAN-MAR
GRADING AND UTILITY INSTALLATION
- Grading and soil export begins
- Start of retaining wall construction
- Underground utility installation on Stevens Ave. access driveway
- Stevens Ave access road final paving.
Q2 2024: APR-JUN
GRADING CONTINUED AND BUILDING FOUNDATIONS
- Grading and soil export continues
- On-site retaining wall construction
- Access driveway from Stevens Ave. complete
- Internal underground utility work begins
- Prepare building foundation pads
Coming Up
Next steps in the revitalization project
Q3 2024: July-Sep
GRADING AND UTILITY WORK CONTINUED
- Anticipated soil mass export completion
- On-site retaining wall construction continued
- Internal underground utility work continued
- Miscellaneous public utility work
Q4 2024: Oct-Dec
SURFACE IMPROVEMENTS BEGIN AND RETAINING WALL CONSTRUCTION CONTINUED
- Start of surface improvements in the First Phase
- Prepare building foundation pads in First Phase
- Continue retaining wall construction
- Continue utility installation
Q1 2025: Jan-Mar
COMPLETION OF RETAINING WALL CONSTRUCTION AND BEGINNING OF VERTICAL CONSTRUCTION
- Start of framing and vertical construction in First Phase
- Completion of retaining wall construction site-wide
- Continued utility installation
- Start of surface improvements in Second Phase
- Prepare building foundation pads in Second Phase