Already Completed

Q3 2023: JUL-SEP

RESIDENT MOVE-OUT & PRE-DEMOLITION WORK

  • Install sound wall at St. James (prior to start of school year)
  • Demolition of Stevens Ave. property
  • Final resident move-outs
  • Ongoing security patrols and building maintenance
  • Lead/asbestos remediation begins
  • Utility disconnection/shutoffs
Q4 2023: OCT-DEC

DEMOLITION AND STEVENS AVE. GRADING

  • Lead/asbestos remediation and utility disconnection/shutoff continues
  • Building demolition begins
  • Site demo and tree removal
  • Grading of Stevens Ave. access driveway for affordable housing site
  • Fencing installation along Nardo Ave.

Coming Up

Next steps in the revitalization project

Q1 2024: JAN-MAR

GRADING AND UTILITY INSTALLATION

  • Grading and soil export begins
  • Start of retaining wall construction
  • Underground utility installation on Stevens Ave. access driveway
  • Stevens Ave access road final paving.
Q2 2024: APR-JUN

GRADING CONTINUED AND BUILDING FOUNDATIONS

  • Grading and soil export continues
  • On-site retaining wall construction
  • Access driveway from Stevens Ave. complete
  • Internal underground utility work begins
  • Prepare building foundation pads
Q3 2024: July-Sep

GRADING AND BUILDING FOUNDATIONS CONTINUED

  • Anticipated soil mass export completion
  • On-site retaining wall construction continued
  • Internal underground utility work continued
  • Ongoing building foundation pad construction