Already Completed

Q3 2023: JUL-SEP

RESIDENT MOVE-OUT & PRE-DEMOLITION WORK

  • Install sound wall at St. James (prior to start of school year)
  • Demolition of Stevens Ave. property
  • Final resident move-outs
  • Ongoing security patrols and building maintenance
  • Lead/asbestos remediation begins
  • Utility disconnection/shutoffs

 

Q4 2023: OCT-DEC

DEMOLITION AND STEVENS AVE. GRADING

  • Lead/asbestos remediation and utility disconnection/shutoff continues
  • Building demolition begins
  • Site demo and tree removal
  • Grading of Stevens Ave. access driveway for affordable housing site
  • Fencing installation along Nardo Ave.

 

Q1 2024: JAN-MAR

GRADING AND UTILITY INSTALLATION

  • Grading and soil export begins
  • Start of retaining wall construction
  • Underground utility installation on Stevens Ave. access driveway
  • Stevens Ave access road final paving.

 

Q2 2024: APR-JUN

GRADING CONTINUED AND BUILDING FOUNDATIONS

  • Grading and soil export continues
  • On-site retaining wall construction
  • Access driveway from Stevens Ave. complete
  • Internal underground utility work begins
  • Prepare building foundation pads

Coming Up

Next steps in the revitalization project

Q3 2024: July-Sep

GRADING AND UTILITY WORK CONTINUED

  • Anticipated soil mass export completion
  • On-site retaining wall construction continued
  • Internal underground utility work continued
  • Miscellaneous public utility work
Q4 2024: Oct-Dec

SURFACE IMPROVEMENTS BEGIN AND RETAINING WALL CONSTRUCTION CONTINUED

  • Start of surface improvements in the First Phase
  • Prepare building foundation pads in First Phase
  • Continue retaining wall construction
  • Continue utility installation
Q1 2025: Jan-Mar

COMPLETION OF RETAINING WALL CONSTRUCTION AND BEGINNING OF VERTICAL CONSTRUCTION

  • Start of framing and vertical construction in First Phase
  • Completion of retaining wall construction site-wide
  • Continued utility installation
  • Start of surface improvements in Second Phase
  • Prepare building foundation pads in Second Phase